Allahabad High Court: Husband's Liability under the Domestic Violence Act Continues Despite Divorce  ||  Bombay HC: Municipal Council Must Pay for Land Used as DP Road Despite Fund Shortage  ||  Uttarakhand HC: Previous Service Pay Protection Does Not Confer Right to Career Progression Benefits  ||  Supreme Court Revives POCSO Case Against Headmistress, Says Verifying Abuse Claims is No Excuse  ||  SC: Voluminous Documents are No Excuse For Their Delayed Production under Commercial Courts Act  ||  Supreme Court Orders Merged Bank's Eviction For Transferring Tenancy Without Landlord's Consent  ||  SC: Oraon Tribe Custom Doesn't Allow Uncle-In-Law to Adopt Niece's Husband as Ghar Damad  ||  Kerala HC Approves New Public Prosecutor Appointment Guidelines After a Minor Revision  ||  Rajasthan HC Clarifies Criminal Writ Petitions Have No Separate Constitutional Status  ||  Delhi HC Clarifies if Whatsapp Acknowledgment Can Make an Arbitral Award Binding    

NCLAT: Cannot Disconnect Electricity Supply During Moratorium Period as Per Section 14(2) of IBC - (27 Feb 2025)

INSOLVENCY

NCLAT New Delhi bench has held that during moratorium period under section 14 of the Insolvency and Bankruptcy Code, 2016 (Code), electricity being an essential supply cannot be disconnected even if no payment is made for such supply.

Tags : NCLAT NEW DELHI   ELECTRICITY SUPPLY   CIRP PERIOD  

Share :        

Disclaimer | Copyright 2026 - All Rights Reserved