SC: Casual Workers Can't be Denied Regularisation if Similar Daily Wagers were Regularised  ||  Supreme Court: Illegal Change of Land Use under Punjab Act Cannot be Legalised Later  ||  Allahabad High Court: Magistrate Must Consider Closure Report Even After Taking Cognizance  ||  Allahabad HC: CGST Arrest Memo Must Include Grounds as Annexure; Reasons to Believe Not Needed  ||  Kerala HC: Petitioner’s Identity Must be Verified Via SHO in Cases of Bank Account Defreezing  ||  J&K&L HC: Undenied Pleadings are Deemed Admitted by Implication under the CPC  ||  Kerala HC: Transfer Order Pending Disciplinary Proceedings Cannot be Disguised as Punishment  ||  Allahabad HC: GST, Incentives, 0r Festival Advances Cannot be Deducted From Employee’s Retiral Dues  ||  SC: Absconding Accused Cannot Claim Anticipatory Bail Solely Because a Co-Accused Was Acquitted  ||  Supreme Court: District Cricket Bodies Must Adopt Good Governance Voluntarily, Not Follow BCCI Rules    

Chetan Sonwalkar Vs. Shriram Properties Pvt. Ltd. and Ors. - (Real Estate Regulatory Authority) (17 Jul 2023)

Complainant is entitled to delay period interest under Section 18 of the Real Estate (Regulation and Development) Act, 2016

MANU/RR/0821/2023

Property

Present complaint is filed under Section 18 of the Real Estate (Regulation and Development) Act, 2016 before this Authority against the project SHRIRAM SUMMITT praying for a direction to pay Delay Period Interest.

On a perusal of the sale agreement, it is seen that the completion date is agreed as 31st December, 2019. The promoter-respondent was required to complete the project and hand over possession of the apartment by 31st December, 12.2019. In cases where the Respondent-promoter has failed to complete or unable to handover the possession of the apartment to the allottee, the Allottee has a right to file a complaint before the Authority and hence, this complaint is admissible for relief in accordance with Section 18 of the Act.

It is evident that complainant have paid sale consideration amount and admittedly there is a delay of more than three years in handing over the apartment as per the agreement. Hence, the complainant is entitled to delay period interest under Section 18 of the Act and accordingly a memo of calculation submitted by the Complainants. Respondent is directed to pay interest on delay period. Complaint allowed.

Tags : INTEREST   DELAY   ENTITLEMENT  

Share :        

Disclaimer | Copyright 2026 - All Rights Reserved