SC: Menstrual Health is a Fundamental Right under Article 21; Orders Free Sanitary Pads in Schools  ||  Supreme Court: Industrial Court is the Proper Forum to Decide Issues Relating to Contract Labour  ||  Supreme Court: Only Civil Court of Original Jurisdiction Can Extend Arbitral Tribunal’s Mandate  ||  SC: Demolition of Private Property Must Rest on Clear Statutory Grounds and Due Consideration  ||  SC: After Complaint Was Withdrawn, BCI Disciplinary Committee Could Not Penalise Advocate  ||  MP HC: Decree Holder Cannot Defeat Compromise or Initiate Execution by Refusing Debtor’s Cheque  ||  MP HC: Spouse’s Income Cannot Be Clubbed With Public Servant’s for Disproportionate Assets Case  ||  Ker HC: Bar Association is Not Employer & Cannot Form Internal Complaints Committee under POSH Act  ||  SC: Ex-Contract Workers Must Be Preferred When Employers Replace Contract Labour With Regular Staff  ||  SC: Waqf Tribunals Cannot Hear Claims over Properties Not Listed or Registered under Waqf Act    

NCDRC to DLF Universals: Refund Entire Amount for Delay in Handing Over Possession - (10 Jan 2023)

CONSUMER

National Consumer Dispute Redressal Commission (NCDRC) has directed DLF Universal to refund entire principal amount of Rs. 37,73,154/- to the complainant along with compensation in the form of simple interest @6% p.a. from for delay in handing over possession.

Tags : NCDRC   DLF UNIVERSAL   COMPENSATION   POSSESSION  

Share :        

Disclaimer | Copyright 2026 - All Rights Reserved