Calcutta HC: Award May Be Set Aside if Tribunal Rewrites Contract or Ignores Key Clauses  ||  Delhi HC Suspends Kuldeep Singh Sengar’s Life Term, Holding Section 5(C) of POCSO Not Made Out  ||  Calcutta High Court: Arbitration Clause in an Expired Lease Cannot be Invoked For a Fresh Lease  ||  Delhi High Court: 120-Day Timeline under Section 132B Of Income Tax Act is Not Mandatory  ||  NCLAT Reaffirms That Borrower's Debt Acknowledgment Also Extends Limitation Period for Guarantors  ||  NCLAT: Oppression & Mismanagement Petition Cannot Be Filed Without Company Membership on Filing Date  ||  Supreme Court Quashes Rajasthan Village Renaming, Says Government Must Follow its Own Policy  ||  NCLAT: NCLT Can Order Forensic Audit on its Own, No Separate Application Required  ||  NCLAT Reiterates That IBC Cannot be Invoked as a Recovery Tool for Contractual Disputes  ||  Delhi HC: DRI or Central Revenues Control Lab Presence in Delhi Alone Does Not Confer Jurisdiction    

Delhi HC: If Contract Is Extended, It Can’t be Allowed to Reduce Extension Period Retrospectively - (09 May 2022)

CONTRACT

Delhi High Court has ruled that when the employer has granted an extension of time to the contractor for a specified period, it cannot turn around to contend that the extension was only provisional and it is allowed to reduce the number of days by which the contract was executed.

Tags : DELHI HIGH COURT   EXTENSION OF TIME   PROVISIONAL   CONTRACT  

Share :        

Disclaimer | Copyright 2025 - All Rights Reserved