Supreme Court: State Must Be Impleaded When Relief is Sought From Public Exchequer  ||  SC: Student Fees Cannot Be Increased Mid-Course Except in Exceptional Circumstances  ||  Supreme Court: ED's Delay in Sending Arrest Order Does Not By Itself Invalidate Arrest  ||  Supreme Court: Appeal Limitation Runs From NCLAT Order Pronouncement, Not Certified Copy Receipt  ||  Gujarat High Court: Waqf Tribunal Has No Supervisory Authority Over Waqf Board  ||  Kerala High Court Orders Aadhaar Fingerprint Comparison to Trace Sreekrishnapuram Murder Culprits  ||  Delhi High Court: Unnatural Death at Police Station Alone Cannot Establish Police Negligence  ||  Orissa High Court: Teacher Scolding Student for Intoxicant Use is Not Suicide Abetment  ||  Supreme Court: Drug Users are Victims and Focus Must Be on Breaking the Supply Chain  ||  Supreme Court: Non-Signatories May Join Arbitration When the Dispute Affects Their Rights    

Government launches one-time settlement Scheme for Contractual Disputes - (02 Aug 2023)

Commercial

The Department of Expenditure, Ministry of Finance, has launched the scheme, "Vivad se Vishwas II - (Contractual Disputes), to effectively settle the pending contractual disputes of government and government undertakings. The scheme was announced in the Union Budget 2023-24 by the Union Finance Minister.The scheme will apply to all domestic contractual disputes where one of the parties is either the Government of India or an organisation working under its control.Last date for submitting claims under the scheme is 31st October, 2023.

Under the scheme, for Court Awards passed on or before 30th April, 2023, the settlement amount offered to the Contractor will be up to 85% of the net amount awarded/ upheld by the court.For Arbitral Awards passed on or before 31st January, 2023, the settlement amount offered is up to 65% of the net amount awarded. Government e-Marketplace (GeM) has developed a dedicated web-page for implementation of this scheme. Eligible claims shall be processed only through GeM. For non-GeM contracts of Ministry of Railways, contractors may register their claims on IREPS (www.ireps.gov.in).

However, the scheme will not be applicable to cases where parties, including the procuring entities, have already reached a settlement through conciliation agreement. Cases under international arbitration are not eligible to be settled under the scheme. The scheme would help in clearing backlog of old pending cases.

Tags : SETTLEMENT SCHEME   LAUNCH   CONTRACTUAL DISPUTES  