SC: Valid Bareboat Charter Termination Extinguishes Demise Charter, Vessel Arrest Vacated  ||  SC: Absence of Train Ticket No Ground to Deny Compensation for Passenger’s Death  ||  Patna HC: Routine FIR Involvement alone cannot Deny Arms Licence without Safety Threat  ||  Chhattisgarh HC: WhatsApp Chats Proving Mental Cruelty cannot be Ignored on Evidence Grounds  ||  Delhi HC: Foreign Travel Restrictions must not Obstruct Pregnant Foreigner's Medical Care  ||  MP High Court: Article 227 Cannot Be Invoked to Quash Wife’s Conjugal Rights Proceedings  ||  Kerala High Court Issues Directions on Driver Profiling, Bus Regulation and Road Safety  ||  Delhi HC: Prior Permission for Foreign Travel Unjustified When Accused Was Never Arrested  ||  Air India Penalised Rs. 50K Over De-boarding Disabled Woman and Wheelchair Damage  ||  Delhi HC: Muslim Personal Law cannot Shield Sex with Minor Wife from POCSO Case    

Central Electricity Authority notifies the National Electricity Plan for the period of 2022-32 - (31 May 2023)

Electricity

The Central Electricity Authority (CEA) has notified the National Electricity Plan (NEP) (Vol-I Generation) for the period of 2022-32. The plan documentincludes the review of the last five years (2017-22), a detailed plan for the next five years (2022-27) and the prospective plan for the next five years (2027-32).Funds to the tune of Rs. 33.60 lakh crore needed for power generation capacity addition from 2022-2032.

According to the NEP document, the projected All India peak electricity demand and electrical energy requirement is 277.2 GW and 1907.8 BU for the year 2026-27 and 366.4 GW and 2473.8 BU for the year 2031-32 as per 20th Electric Power Survey (EPS) Demand projections. The Energy Requirement and Peak Demand are inclusive of the impact due to increased adoption of Electric Vehicles, Installation of Solar roof tops, Production of Green hydrogen, Saubhagya scheme etc.The projection of total capacity addition is in line with the target of the country to achieve a non-fossil based installed capacity of around 500 GW by the year 2029-30.NEP envisages that the share of non-fossil based capacity is likely to increase to 57.4% by the end of 2026-27 and may likely to further increase to 68.4% by the end of 2031-32 from around 42.5% as on April, 2023.

Electricity Act, 2003 has been enacted and came into force from 15.06.2003. The objective is to introduce competition, protect consumer’s interests and provide power for all. The Act provides for National Electricity Policy, Rural Electrification, Open access in transmission, phased open access in distribution, mandatory SERCs, license free generation and distribution, power trading, mandatory metering and stringent penalties for theft of electricity.As per Section 3(4) of the Electricity Act, 2003, Central Electricity Authority has been mandated to prepare a National Electricity Plan (NEP) in accordance with the National Electricity Policy and notify such plan once in five years.

Tags : NEP   NOTIFICATION   REVIEW  