Supreme Court: Second Bail Order Must Record Changed Circumstances or Fresh Grounds  ||  SC: Severity of Injury Alone Cannot Prove Attempt to Murder Without Intent to Cause Death  ||  SC: Promissory Estoppel Cannot Be Used to Claim Unintended Benefits, Lays Down Principles  ||  Kerala High Court: No Unrestricted RTI; DPDP Act Strengthens Privacy Framework  ||  Allahabad High Court: Juvenile Offence Case Does Not Bar Govt Job In Adulthood  ||  Gauhati HC: Burden Of Proving Citizenship Stays With Proceedee and Does Not Shift At Any Stage  ||  Delhi HC: Property Disputes Between In-Laws and Daughter-In-Law are Not Exclusively For Family Court  ||  Delhi High Court: After Probate is Granted, A Will Does Not Require Fresh Proof under Section 68  ||  Ker HC: Periodic Replacement and Maintenance of Prosthetic Limb Must Be Included in Compensation  ||  Madras High Court: DNA Test Not Required For Mother to Donate Kidney to Her Son    

Central Electricity Authority notifies the National Electricity Plan for the period of 2022-32 - (31 May 2023)

Electricity

The Central Electricity Authority (CEA) has notified the National Electricity Plan (NEP) (Vol-I Generation) for the period of 2022-32. The plan documentincludes the review of the last five years (2017-22), a detailed plan for the next five years (2022-27) and the prospective plan for the next five years (2027-32).Funds to the tune of Rs. 33.60 lakh crore needed for power generation capacity addition from 2022-2032.

According to the NEP document, the projected All India peak electricity demand and electrical energy requirement is 277.2 GW and 1907.8 BU for the year 2026-27 and 366.4 GW and 2473.8 BU for the year 2031-32 as per 20th Electric Power Survey (EPS) Demand projections. The Energy Requirement and Peak Demand are inclusive of the impact due to increased adoption of Electric Vehicles, Installation of Solar roof tops, Production of Green hydrogen, Saubhagya scheme etc.The projection of total capacity addition is in line with the target of the country to achieve a non-fossil based installed capacity of around 500 GW by the year 2029-30.NEP envisages that the share of non-fossil based capacity is likely to increase to 57.4% by the end of 2026-27 and may likely to further increase to 68.4% by the end of 2031-32 from around 42.5% as on April, 2023.

Electricity Act, 2003 has been enacted and came into force from 15.06.2003. The objective is to introduce competition, protect consumer’s interests and provide power for all. The Act provides for National Electricity Policy, Rural Electrification, Open access in transmission, phased open access in distribution, mandatory SERCs, license free generation and distribution, power trading, mandatory metering and stringent penalties for theft of electricity.As per Section 3(4) of the Electricity Act, 2003, Central Electricity Authority has been mandated to prepare a National Electricity Plan (NEP) in accordance with the National Electricity Policy and notify such plan once in five years.