Allahabad High Court : Deceased Farmer’s Odd Jobs Don’t Bar Family from Scheme Benefits  ||  Secured Creditors' Dues Take Priority Over Govt Claims: Allahabad HC on SARFAESI & RDB Acts  ||  Daughter Can’t Claim Mitakshara Father’s Property if He Died Pre-1956 & Son Survives: HC  ||  Gujarat High Court: Sessions Court Can’t Suspend Sentence Just to Allow Revision Filing  ||  Delhi High Court: Non-Combat Security Roles Crucial; Minor Lapse Risks National Safety  ||  Punjab & Haryana HC: Allegation of Harassment Alone Insufficient to Prove Abetment to Suicide  ||  Orissa HC: Directors Liable under S.138 NI Act Despite Company’s Insolvency  ||  Bombay HC: GST Return Details of Company Exempt from Disclosure under RTI Act  ||  Chhattisgarh HC: Timely Appointment of Electronic Evidence Examiners Vital in Cyber Crime Probes  ||  Bombay HC: GST Return Details of Company Exempt from Disclosure under RTI Act    

Whispering Tower Flat Owner Welfare Association Vs. Abhay Narayan Manudhane, RP of the Corporate Debtor and Ors. - (NATIONAL COMPANY LAW APPELLATE TRIBUNAL) (04 Jan 2022)

Insolvency resolution process has to be completed within 330 days maximum, but in exceptional cases, the period can be extended by Adjudicating Authority/Appellate Tribunal

MANU/NL/0007/2022

Insolvency

Present Appeals have been filed against judgment passed by the National Company Law Tribunal, Mumbai Bench, rejecting the application filed by the Resolution Professional seeking extension of Corporate Insolvency Resolution Process (CIRP). All the Appellants are aggrieved by the rejection of Application filed by Resolution Professional before the Adjudicating Authority for extension of CIRP period.

The object of the IB Code is the resolution of the insolvency of a Corporate Debtor. Efforts of all stakeholders have to be towards resolution of insolvency. There can be no dispute that, the law mandates that CIRP proceedings have to be concluded within 330 days. Hon'ble Supreme Court, after noticing the above requirement of 330 days in Section 12, laid down in Committee of Creditors of Essar Steel India Ltd. vs. Satish Kumar Gupta and Ors. that normally as per law, insolvency resolution process has to be completed within 330 days maximum, but in exceptional cases, the period can be extended by Adjudicating Authority/Appellate Tribunal.

The Hon'ble Supreme Court time and again reminded that, the object of IBC is to resolve the insolvency resolution process and liquidation is to be adopted as a last resort. The Tribunal in the facts of the present case are of the view that, Adjudicating Authority ought to have given reasonable extension of period for proceeding further with Resolution Project Wise for which 25 Expression of Interests have already been received with the Resolution Professional.

The order of the Adjudicating Authority is set aside. Extension of 90 days is granted from the date of this order during which period the Resolution Professional and the Committee of Creditors may complete the Project Wise Resolution as decided in their meeting on 8th September, 2021. Appeal allowed.

Tags : PERIOD   EXTENSION   ENTITLEMENT  