J&K&L High Court: Illegal Occupation of Shamilat Land Cannot Become Legal Right  ||  Bombay HC: Land Reservation Lapses if No Acquisition Within 24 Months of Purchase Notice  ||  Gujarat High Court: Conditional Sale Mortgage Differs From Sale with Repurchase  ||  Calcutta High Court: Transfer to Commercial Court No Bar to Counterclaim with Leave  ||  Calcutta High Court: FIR Delay Not Fatal; Insurer Must Prove Policy Breach for Recovery  ||  Madras High Court: State Temple Festivals Must Not Perpetuate Caste, Aim to Annihilate it  ||  Calcutta HC: Economic Abuse Enables DV Case at Current Residence  ||  Calcutta HC: Economic Abuse Enables DV Case at Current Residence  ||  Bom.HC: Courts have no Discretion to Award Lesser Sentence When Law Prescribes Minimum Punishment  ||  Bombay HC: Single Mother Recognized as Complete Parent for Child’s Identity    

Whispering Tower Flat Owner Welfare Association Vs. Abhay Narayan Manudhane, RP of the Corporate Debtor and Ors. - (NATIONAL COMPANY LAW APPELLATE TRIBUNAL) (04 Jan 2022)

Insolvency resolution process has to be completed within 330 days maximum, but in exceptional cases, the period can be extended by Adjudicating Authority/Appellate Tribunal

MANU/NL/0007/2022

Insolvency

Present Appeals have been filed against judgment passed by the National Company Law Tribunal, Mumbai Bench, rejecting the application filed by the Resolution Professional seeking extension of Corporate Insolvency Resolution Process (CIRP). All the Appellants are aggrieved by the rejection of Application filed by Resolution Professional before the Adjudicating Authority for extension of CIRP period.

The object of the IB Code is the resolution of the insolvency of a Corporate Debtor. Efforts of all stakeholders have to be towards resolution of insolvency. There can be no dispute that, the law mandates that CIRP proceedings have to be concluded within 330 days. Hon'ble Supreme Court, after noticing the above requirement of 330 days in Section 12, laid down in Committee of Creditors of Essar Steel India Ltd. vs. Satish Kumar Gupta and Ors. that normally as per law, insolvency resolution process has to be completed within 330 days maximum, but in exceptional cases, the period can be extended by Adjudicating Authority/Appellate Tribunal.

The Hon'ble Supreme Court time and again reminded that, the object of IBC is to resolve the insolvency resolution process and liquidation is to be adopted as a last resort. The Tribunal in the facts of the present case are of the view that, Adjudicating Authority ought to have given reasonable extension of period for proceeding further with Resolution Project Wise for which 25 Expression of Interests have already been received with the Resolution Professional.

The order of the Adjudicating Authority is set aside. Extension of 90 days is granted from the date of this order during which period the Resolution Professional and the Committee of Creditors may complete the Project Wise Resolution as decided in their meeting on 8th September, 2021. Appeal allowed.

Tags : PERIOD   EXTENSION   ENTITLEMENT  