P&H HC Quashes Case over Allegations Against Judge, Orders Police Awareness on S.215 BNSS  ||  Chhattisgarh HC: Scheduled Tribe Persons Can Voluntarily Choose to be Governed by Hindu Marriage Act  ||  Kerala HC: Intra-Court Appeal Maintainable Against Ex Parte Ad Interim Orders Affecting Remedies  ||  Kerala HC: Failure To Record Victim’s Intellectual Disability isn’t Fatal if Competent to Testify  ||  Calcutta HC Reduces Man's Sentence, Holding Bamboo Stick or Rod Not A Weapon Likely To Cause Death  ||  Kerala HC: Siblings Cannot Claim Compensation for ‘Loss of Love’ in Motor Accident Death Cases  ||  Gujarat HC: Judicial Fixation of Standard Rent Inapplicable to New Construction After 2001 Amendment  ||  Orissa HC: 60-Day Disposal of DV Act Plea May Not be Practical but Long Adjournments Must be Avoided  ||  Madras HC: Minister Regupathy Gave a Mischievous Political Twist to the Thiruparankundram Issue  ||  Jharkhand HC Cautions Officers, Says Citing Proposed SLP in SC to Delay Compliance is ‘In Bad Faith’    

Whispering Tower Flat Owner Welfare Association Vs. Abhay Narayan Manudhane, RP of the Corporate Debtor and Ors. - (NATIONAL COMPANY LAW APPELLATE TRIBUNAL) (04 Jan 2022)

Insolvency resolution process has to be completed within 330 days maximum, but in exceptional cases, the period can be extended by Adjudicating Authority/Appellate Tribunal

MANU/NL/0007/2022

Insolvency

Present Appeals have been filed against judgment passed by the National Company Law Tribunal, Mumbai Bench, rejecting the application filed by the Resolution Professional seeking extension of Corporate Insolvency Resolution Process (CIRP). All the Appellants are aggrieved by the rejection of Application filed by Resolution Professional before the Adjudicating Authority for extension of CIRP period.

The object of the IB Code is the resolution of the insolvency of a Corporate Debtor. Efforts of all stakeholders have to be towards resolution of insolvency. There can be no dispute that, the law mandates that CIRP proceedings have to be concluded within 330 days. Hon'ble Supreme Court, after noticing the above requirement of 330 days in Section 12, laid down in Committee of Creditors of Essar Steel India Ltd. vs. Satish Kumar Gupta and Ors. that normally as per law, insolvency resolution process has to be completed within 330 days maximum, but in exceptional cases, the period can be extended by Adjudicating Authority/Appellate Tribunal.

The Hon'ble Supreme Court time and again reminded that, the object of IBC is to resolve the insolvency resolution process and liquidation is to be adopted as a last resort. The Tribunal in the facts of the present case are of the view that, Adjudicating Authority ought to have given reasonable extension of period for proceeding further with Resolution Project Wise for which 25 Expression of Interests have already been received with the Resolution Professional.

The order of the Adjudicating Authority is set aside. Extension of 90 days is granted from the date of this order during which period the Resolution Professional and the Committee of Creditors may complete the Project Wise Resolution as decided in their meeting on 8th September, 2021. Appeal allowed.

Tags : PERIOD   EXTENSION   ENTITLEMENT  